Measured Depth will be off next week for Thanksgiving. Enjoy the turkey and football, and I’ll be back on December 1 to conclude this series (barring any breaking news!).
Southeast utilities are backstopping a historically large buildout in natural gas pipeline capacity, and forthcoming Northeast-to-Southeast projects will erode the Southeast’s pull on Gulf Coast supplies. But demand in the region is growing strongly enough that utilities are also backstopping projects to pull more gas from the west: Kinder Morgan’s ~2 Bcfd Mississippi Crossing on Tennessee Gas Pipeline and Boardwalk’s ~1.1 Bcfd Kosciusko Junction on Gulf South.
These projects will both meet growing Southeast demand and displace more expensive gas now moving from southeast Louisiana to Mississippi. But as I’ll show, Kosi Junction adds less effective capacity into the Southeast than its nameplate suggests, because some gas already reaches the region on this route. And because both projects’ capacity steps up farther east, filling them requires competing for Gulf-bound flows on Columbia Gulf and Texas Eastern.
What do these projects do?
Gulf South’s ~1.1 Bcfd Kosciusko Junction project, due online in the second half of 2028, consists of three pieces:
The sale of Texas Gas’s Greenville Lateral to Gulf South. The Greenville Lateral moves gas from the Texas Gas mainline in Greenville, Mississippi, to an interconnect with TETCO in Kosciusko, Mississippi. Between Greenville and Kosciusko, the project adds a new lateral and interconnect with Columbia Gulf at Inverness, Mississippi. (The Greenville Lateral also moves ~300 MMcfd to Kosciusko from existing contracts, but I’ve netted those contracts and flows out throughout this post to focus only on the project’s capacity.)
A new-build 36-inch pipe from Kosciusko to the existing Gulf South 42-inch mainline in Clarke County, Mississippi.
Existing capacity on Gulf South from Clarke County to its Transco interconnect at Station 85 in Alabama.
TGP’s ~2 Bcfd Mississippi Crossing is also due online in the second half of 2028. MSX consists of a new west-to-east leg that originates at TGP’s 100 leg near Greenville, connects with Columbia Gulf, TGP’s 800 leg, and TETCO, and then delivers into TGP’s 500 leg, SoNat, and Transco. SoNat’s downstream SSE4 project, due online in the fourth quarter of 2028, will move ~800 MMcfd from MSX to power plants farther east.
On both projects, capacity steps up at Inverness/Isola and again at Kosciusko, as shown in the bottom panel of Figure 1.
Figure 1 | Forthcoming Southeast projects